| FOOTINGS FOUNDATION | JAS1 | PASS | 483704 | 6/28/2021 9:14:34 AM
Pilings for shoring numbers three through 18 and 20 with SOR and soils report
|
|
| STRUCTURAL CONCRETE | Murray Armstrong | PASS | 14502 | 7/7/2021 9:37:51 AM
Placement of piles times 20, noted on site plans. Received deputies report and soil's
|
|
| STRUCTURAL CONCRETE | JAS2 | PARTIAL | 05902 | 7/16/2021 11:49:25 AM
Ok to place conc shoring piles 1,2,39,40,41,42,43,44,45,46,47,48,49 & 50
Supporting docs received.
|
|
| FOOTINGS FOUNDATION | JAS1 | PARTIAL | 484804 | 11/9/2021 9:51:38 AM
From S/W corner to as noted on plan with SOR
Need deputy report for cleaning
|
|
| FOOTINGS FOUNDATION | Murray Armstrong | PASS | 594302 | 12/1/2021 8:45:11 AM
Shot Crete walls at 1/2 of north elevation entire east and south elevation. SOR received and deputies report will be emailed to me
|
|
| RAISED FLOOR FRAMING | JAS1 | CORRECTIONS | 474702 | 6/16/2022 10:03:16 AM
Structural walls at elevator and stairwell
Missing ties at top of one pilaster
Picked up SOR
|
|
| STRUCTURAL CONCRETE | JAS1 | PASS | 41302 | 6/22/2022 10:29:03 AM
Walls at basement elevator and stairwell
|
|
| STRUCTURAL CONCRETE | JAS1 | CORRECTIONS | 305802 | 7/21/2022 10:34:51 AM
Not ready
7/21/2022 11:11:03 AM
Not ready
|
|
| STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 34102 | 7/28/2022 9:09:24 AM
Ground level concrete deck approved
|
|
| STRUCTURAL CONCRETE | VCA3 | PASS | 49704 | 12/16/2022 8:42:30 AM
2nd floor deck rebar with SOR and deputy report
|
|
| FLOOR SHEATHING | Murray Armstrong | PASS | 54722 | 4/4/2023 9:59:37 AM
At L-4
|
|
| FLOOR SHEATHING | VCA3 | PARTIAL | 01020 | 4/27/2023 11:24:41 AM
Pending SOR report
|
|
| ROOF SHEATHING | VCA3 | CORRECTIONS | | 6/2/2023 12:05:58 PM
Supply SOR and deputy report for roof sheathing, then call inspection
|
|
| ROOF SHEATHING | VCA3 | PASS | 38803 | 6/9/2023 11:15:29 AM
With SOR
|
|
| ROUGH FRAMING | VCA3 | PARTIAL | 481637 | 7/3/2023 9:57:54 AM
Exterior shear walls with SOR and deputy report
|
|
09/08/2023 | DENSGLASS | Phil Brandenburg | PASS | 24818 | 9/8/2023 10:29:02 AM
Dens glass at exterior only
|
|
09/18/2023 | DENSGLASS | Murray Armstrong | PASS | 175718 | 9/18/2023 9:09:08 AM
Second layer of exterior gypsum up to L3
|
|
09/20/2023 | INTERIOR WALL FRAMG | Murray Armstrong | PARTIAL | 6328 | 9/20/2023 9:38:04 AM
I spoke with project manager, and I indicated to him that we would not be approving prelim areas for insulation until roof has been installed.
|
|
12/06/2023 | FOOTINGS/FOUNDATION | Murray Armstrong | PARTIAL | | 12/6/2023 8:54:59 AM
Canceled
|
|
12/07/2023 | RAISED FLOOR FRAMING | Murray Armstrong | PARTIAL | | 12/7/2023 10:21:28 AM
Approved second layer of drywall and shaft
|
|
12/11/2023 | ROUGH FRAMING | VCA3 | CORRECTIONS | | 12/12/2023 6:33:11 AM
Not ready
|
|
01/16/2024 | SHEARWALL | Murray Armstrong | PASS | 491805 | 1/16/2024 10:32:54 AM
Approve framing, pending SOR report. Project is approved to proceed with pre-lim
|
|
03/21/2024 | ROUGH FRAMING | Murray Armstrong | PASS | | 3/21/2024 9:10:27 AM
At L4 and L5, received structural observation
|
|
04/02/2024 | ROUGH FRAMING | Phil Brandenburg | PARTIAL | | 4/2/2024 9:16:12 AM
Second and third floor approved
|
|
04/04/2024 | ROUGH FRAMING | Phil Brandenburg | PARTIAL | | 4/4/2024 9:16:43 AM
OK to install ceilings at lower units
|
|
04/05/2024 | ROUGH FRAMING | Phil Brandenburg | CORRECTIONS | | 4/5/2024 7:47:19 AM
Canceled per contractor
|
|
04/15/2024 | INSULATION | Phil Brandenburg | PARTIAL | | 4/15/2024 8:46:48 AM
L3 and L4 approved
|
|
04/16/2024 | INSULATION | Phil Brandenburg | PARTIAL | | 4/16/2024 9:33:55 AM
Installation on going
|
|
04/17/2024 | INSULATION | Phil Brandenburg | PARTIAL | | 4/17/2024 6:35:15 AM
currently installing
|
|
05/02/2024 | EXTERIOR LATH | Murray Armstrong | PARTIAL | | 5/2/2024 10:23:53 AM
Cheerier, less, with exception of area at manlift and areas to receive glass.
|
|
05/15/2024 | INSULATION | Murray Armstrong | PARTIAL | 155517 | 5/15/2024 9:38:54 AM
Partial insulation inspection at units, areas with fire sprinklers did not have insulation installed as a were waiting for fire sprinkler inspection
|
|