| ROUGH ELECTRICAL | JAS1 | PARTIAL | 143630 | |
|
| ROUGH ELECTRICAL | JAS1 | PARTIAL | 5905 | 12/7/2020 9:15:07 AM
In slab 1st floor
|
|
| ROUGH ELECT WALLS | JAS1 | PARTIAL | 171103 | 8/31/2021 9:29:33 AM
Add fire pads at party walls
|
|
| ROUGH WIRING | JAS1 | PARTIAL | 163902 | 8/31/2021 9:29:37 AM
In progress waiting for drop ceiling completion
|
|
| ROUGH ELECTRICAL | JAS1 | CORRECTIONS | 375702 | 10/29/2021 10:33:42 AM
Ground all metal boxes
Lights required to illuminate exterior doorways
Fourth floor needs completion
|
|
| ROUGH WIRING | JAS1 | CORRECTIONS | 455406 | |
|
| ROUGH ELECTRICAL | JAS1 | CORRECTIONS | 45005 | |
|
| ROUGH ELECTRICAL | Murray Armstrong | PARTIAL | 71505 | 12/7/2021 9:30:22 AM
Exterior lighting added to five units at ground floor
|
|
| ROUGH ELECTRICAL | Murray Armstrong | PARTIAL | | 12/8/2021 8:58:25 AM
Performed yesterday
|
|
02/07/2022 | ROUGH ELECT CEILING | JAS2 | PARTIAL | 392905 | 2/7/2022 4:17:15 PM
Previously approved
|
|
02/07/2022 | ROUGH ELECT CEILING | JAS2 | PARTIAL | 382704 | 2/7/2022 4:17:18 PM
Previously approved
|
|
02/22/2022 | SERVICE | JAS1 | PARTIAL | 482406 | 2/22/2022 10:42:51 AM
Discussed any potential change to service entrance conductors
Also approved insulation third and fourth floor
|
|
09/08/2022 | FINAL ELECTRICAL** | VCA3 | CORRECTIONS | 381711 | 9/8/2022 11:51:34 AM
Not ready
|
|
02/24/2023 | FINAL ELECTRICAL** | VCA3 | CORRECTIONS | 0205 | 2/24/2023 1:34:24 PM
Not ready
|
|
06/14/2023 | UNDERGROUND ELECT | Murray Armstrong | PARTIAL | 174907 | 6/14/2023 9:14:32 AM
None observed
|
|
11/28/2023 | FINAL ELECTRICAL | Murray Armstrong | CORRECTIONS | | 11/28/2023 10:10:10 AM
Not ready, mechanical contractor met me there, said he wanted his final, so he get paid, I told him we final all trades at one time. The job is not anywhere close to being ready for final at this time.
|
|
02/26/2024 | UNDERGROUND ELECT | Phil Brandenburg | CORRECTIONS | 284327 | 2/26/2024 8:51:13 AM
Site meeting only to discuss main feed entrance into building
|
|
| SERVICE | INSPECTOR BUCKET | | | |
|
| FINAL ELECTRICAL** | INSPECTOR BUCKET | | | |
|
| ROUGH ELECT CEILING | INSPECTOR BUCKET | | | |
|
04/15/2024 | ROUGH ELECTRICAL | Phil Brandenburg | CORRECTIONS | | 4/15/2024 8:57:21 AM
Second attempt no one on job locked
Will charge if next inspection missed
|
|
04/26/2024 | ROUGH ELECTRICAL | Phil Brandenburg | PARTIAL | | 4/26/2024 9:33:34 AM
Site meeting to discuss main disconnects for building
|
|