 11/17/2022FOOTINGS/FOUNDATIONPhil BrandenburgPARTIAL11/17/2022 8:16:44 AM Shoring over 75% complete

 02/28/2023FOOTINGS/FOUNDATIONPhil BrandenburgPARTIAL2/28/2023 8:14:39 AM No progress due to rain

 03/02/2023FOOTINGS/FOUNDATIONPhil BrandenburgPARTIAL3/2/2023 8:08:52 AM Continued work on footings

 03/08/2023FOOTINGS FOUNDATIONMurray ArmstrongPASS3044123/8/2023 10:14:53 AM At P-3 Reinforcement at footings and foundations for the following, perimeter walls, interior spread footings, pads, Crane, Mat foundation

 04/05/2023FOOTINGS FOUNDATIONPhil BrandenburgPARTIAL5047044/5/2023 9:12:48 AM Columns and elevator walls

 04/07/2023FOOTINGS/FOUNDATIONPhil BrandenburgPARTIAL4/7/2023 8:10:29 AM Site meeting only

 04/19/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL4/19/2023 7:57:23 AM Continued work at slab on grade

 04/26/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL1334044/26/2023 9:19:15 AM Slab on grade at basement level

 05/05/2023SHEARWALLPhil BrandenburgPARTIAL5737035/5/2023 8:55:28 AM South and east sheer walls first level

 05/09/2023SHEARWALLPhil BrandenburgPARTIAL256075/9/2023 9:02:17 AM Continued work at basement shot Crete walls

 05/15/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL2842275/15/2023 8:52:31 AM Remaining first lift shot Crete walls west section

 05/16/2023SHEARWALLPhil BrandenburgPARTIAL944115/16/2023 8:13:16 AM Final section lower western shearwall approved

 05/18/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL5/18/2023 8:00:00 AM Continued progress at L2 slab supports

 05/25/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL1727045/25/2023 9:39:17 AM P2 deck approved

 06/01/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL3749096/1/2023 9:26:14 AM Columns as noted

 06/06/2023SHEARWALLMurray ArmstrongPASS4515146/6/2023 9:28:10 AM Perimeter shot Crete wall, reinforcement at P2 level, as noted on approved plans. 4/0 ground to building steel.

 06/08/2023SHEARWALLPhil BrandenburgPARTIAL1054166/8/2023 8:42:48 AM Remaining western sheer walls

 06/13/2023SHEARWALLPhil BrandenburgPARTIAL3937056/13/2023 8:54:55 AM Final sheer wall western section 1st level above basement

 06/29/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL1219036/29/2023 10:11:22 AM L2 deck approved

 07/05/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL4450077/5/2023 8:46:22 AM L1 columns approved

 07/06/2023FOOTINGS/FOUNDATIONPhil BrandenburgPARTIAL7/6/2023 7:55:35 AM Continued work at level one walls

 07/10/2023SHEARWALLMurray ArmstrongPASS1129077/10/2023 11:09:49 AM Perimeter shot Crete walls at P1 up through mezzanine, and interior sheer wall reinforcement as noted on approved plans

 07/12/2023SHEARWALLPhil BrandenburgPARTIAL4310177/12/2023 9:02:37 AM Remaining shear walls, L-1 level

 07/18/2023SHEARWALLPhil BrandenburgPARTIAL7/18/2023 4:52:33 PM L1 shear south

 07/19/2023SHEARWALLPhil BrandenburgCORRECTIONS597127/19/2023 8:44:17 AM Not ready

 07/20/2023SHEARWALLPhil BrandenburgPARTIAL5954237/20/2023 9:20:18 AM Remaining L1, shear walls and ramp

 07/31/2023GROUT LIFTMurray ArmstrongPASS04087/31/2023 10:26:53 AM As noted 7/31/2023 10:27:49 AM As noted

 08/01/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL2357168/1/2023 7:57:46 AM Ground level deck approved

 08/02/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL5635138/2/2023 8:42:03 AM Continued work at ground floor

 08/04/2023STRUCTURAL CONCRETEPhil BrandenburgPASS348198/4/2023 8:51:41 AM Ground level deck, eastern half

 08/10/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL859228/10/2023 8:54:38 AM Remaining L1 deck, except ramp

 09/18/2023SHEARWALLPhil BrandenburgPARTIAL16129/18/2023 8:17:47 AM Small ground level walls as noted

 09/25/2023SHEARWALLPhil BrandenburgPARTIAL836119/25/2023 9:33:08 AM Ground level, sheer walls and column as noted

 10/09/2023SHEARWALLPhil BrandenburgPARTIAL43461210/9/2023 8:45:41 AM Shear walls as noted

 10/10/2023SHEARWALLPhil BrandenburgPARTIAL

 10/12/2023SHEARWALLPhil BrandenburgPARTIAL41552610/12/2023 9:01:02 AM Continued ground level, sheer walls as noted

 10/13/2023SHEARWALLPhil BrandenburgPARTIAL

 10/16/2023SHEARWALLPhil BrandenburgPARTIAL10/16/2023 6:23:02 AM ground level as noted

 10/17/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL10/17/2023 6:17:07 AM continued shear walls

 10/18/2023SHEARWALLPhil BrandenburgCORRECTIONS9102710/18/2023 11:56:49 AM Canceled per contractor

 10/20/2023SHEARWALLPhil BrandenburgPARTIAL15462210/20/2023 8:09:04 AM Radius wall as shown on plan ground level

 10/25/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL48522610/25/2023 9:22:43 AM Small decks as noted

 11/02/2023SHEARWALLPhil BrandenburgPARTIAL

 11/07/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL2901411/7/2023 8:51:03 AM Shear walls only at western portion of site

 11/07/2023SHEARWALLPhil BrandenburgPARTIAL25501311/7/2023 8:51:05 AM Shear walls only at western portion of site

 11/08/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL29150511/8/2023 9:12:02 AM Second floor deck, approved, pending minor change, RFI

 11/22/2023SHEARWALLPhil BrandenburgPARTIAL56192111/22/2023 9:32:40 AM Shear walls as noted. Also verified underground for generator

 11/28/2023SHEARWALLPhil BrandenburgPARTIAL52330311/28/2023 8:54:00 AM Second level walls as noted

 12/05/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL19490412/5/2023 8:14:34 AM Ramp rebar as noted

 12/06/2023INTERIOR DRYWALLVCA3PARTIAL36342412/6/2023 11:27:46 AM Provide fire tapping at shaft wall joint

 12/07/2023INTERIOR DRYWALLVCA3CORRECTIONS3802512/7/2023 11:14:19 AM Not ready

 12/18/2023STRUCTURAL CONCRETEPhil BrandenburgPARTIAL53132612/18/2023 8:19:05 AM Level two western deck

 01/05/2024STRUCTURAL CONCRETEPhil BrandenburgPARTIAL173101/5/2024 7:09:49 AM Continued observations of second-floor concrete areas

 01/08/2024STRUCTURAL CONCRETEMurray ArmstrongPARTIAL734161/8/2024 9:52:33 AM Sheer walls at L2, west elevation, partial

 01/09/2024SHEARWALLPhil BrandenburgPARTIAL618411/9/2024 8:21:47 AM Second level walls and columns as noted 1/9/2024 8:29:07 AM Second level walls and columns as noted 1/9/2024 8:37:30 AM Second level walls and columns as noted 1/9/2024 8:47:35 AM Second level walls and columns as noted 1/9/2024 8:53:22 AM Second level walls and columns as noted 1/9/2024 9:15:31 AM Second level walls and columns as noted 1/9/2024 10:07:34 AM Second level walls and columns as noted

 01/29/2024STRUCTURAL CONCRETEPhil BrandenburgPARTIAL3123151/29/2024 8:19:57 AM Third level east deck approved

 02/09/2024SHEARWALLPhil BrandenburgPARTIAL368092/9/2024 9:15:00 AM Third level shear walls as noted

 02/12/2024SHEARWALLPhil BrandenburgPARTIAL3649102/12/2024 8:31:27 AM Remaining third floor, sheer walls

 02/27/2024STRUCTURAL CONCRETEPhil BrandenburgPARTIAL837122/27/2024 8:30:41 AM Third-floor west deck

 02/28/2024STRUCTURAL CONCRETEPhil BrandenburgPARTIAL5540192/28/2024 8:21:16 AM Third floor columns Waste and storm drain systems P1 level

SHEARWALLINSPECTOR BUCKET

 04/04/2024FOOTINGS/FOUNDATIONPhil BrandenburgPARTIAL4/4/2024 9:46:40 AM Third-floor roof slab complete

 04/10/2024STRUCTURAL CONCRETEPhil BrandenburgPASS592274/10/2024 8:09:45 AM Roof

 04/17/2024INTERIOR DRYWALLPhil BrandenburgPARTIAL3039084/17/2024 8:06:13 AM Interior walls at mechanical rooms as noted

 04/17/2024INTERIOR WALL FRAMGPhil BrandenburgPARTIAL2838074/17/2024 8:06:16 AM Interior walls at mechanical rooms as noted

 04/22/2024RATED SHAFT CONSTRPhil BrandenburgPARTIAL518254/22/2024 7:55:42 AM Various rated walls, drywall, and framing as noted

 04/23/2024STEEL FRAMINGPhil BrandenburgPARTIAL1035064/23/2024 8:44:57 AM Progress inspection at lower levels approved

 04/23/2024INSULATIONPhil BrandenburgPARTIAL408264/23/2024 8:45:00 AM Progress inspection at lower levels approved

 04/24/2024INSULATIONPhil BrandenburgPARTIAL544044/24/2024 8:12:26 AM Progress inspection, various floors, including framing, and drywall

 04/25/2024PRE WRAPPhil BrandenburgPARTIAL830054/25/2024 7:57:11 AM Framing and drywall inspections, various levels

 04/25/2024INTERIOR DRYWALLPhil BrandenburgPARTIAL5459204/25/2024 7:57:14 AM Framing and drywall inspections, various levels

 04/25/2024INTERIOR WALL FRAMGPhil BrandenburgPARTIAL5348194/25/2024 7:57:16 AM Framing and drywall inspections, various levels

 05/01/2024RATED SHAFT CONSTRPhil BrandenburgPARTIAL1942185/1/2024 8:21:13 AM Various shaft walls multiple levels

 05/02/2024INTERIOR WALL FRAMGPhil BrandenburgPARTIAL203519

 05/03/2024ROUGH FRAMINGPhil BrandenburgPARTIAL5/3/2024 8:12:21 AM Ongoing framing and drywall at P1 level and ground level

 05/03/2024INTERIOR DRYWALLPhil BrandenburgPARTIAL2235205/3/2024 8:12:24 AM Ongoing framing and drywall at P1 level and ground level

 05/07/2024ROUGH FRAMINGPhil BrandenburgPARTIAL5/7/2024 7:55:41 AM Insulation at various walls, various floors

 05/10/2024INTERIOR DRYWALLPhil BrandenburgPARTIAL5/10/2024 8:39:36 AM Various walls at P1, P2, and L1 as noted