11/17/2022 | FOOTINGS/FOUNDATION | Phil Brandenburg | PARTIAL | | 11/17/2022 8:16:44 AM
Shoring over 75% complete
|
|
02/28/2023 | FOOTINGS/FOUNDATION | Phil Brandenburg | PARTIAL | | 2/28/2023 8:14:39 AM
No progress due to rain
|
|
03/02/2023 | FOOTINGS/FOUNDATION | Phil Brandenburg | PARTIAL | | 3/2/2023 8:08:52 AM
Continued work on footings
|
|
03/08/2023 | FOOTINGS FOUNDATION | Murray Armstrong | PASS | 304412 | 3/8/2023 10:14:53 AM
At P-3 Reinforcement at footings and foundations for the following, perimeter walls, interior spread footings, pads, Crane, Mat foundation
|
|
04/05/2023 | FOOTINGS FOUNDATION | Phil Brandenburg | PARTIAL | 504704 | 4/5/2023 9:12:48 AM
Columns and elevator walls
|
|
04/07/2023 | FOOTINGS/FOUNDATION | Phil Brandenburg | PARTIAL | | 4/7/2023 8:10:29 AM
Site meeting only
|
|
04/19/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | | 4/19/2023 7:57:23 AM
Continued work at slab on grade
|
|
04/26/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 133404 | 4/26/2023 9:19:15 AM
Slab on grade at basement level
|
|
05/05/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 573703 | 5/5/2023 8:55:28 AM
South and east sheer walls first level
|
|
05/09/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 25607 | 5/9/2023 9:02:17 AM
Continued work at basement shot Crete walls
|
|
05/15/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 284227 | 5/15/2023 8:52:31 AM
Remaining first lift shot Crete walls west section
|
|
05/16/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 94411 | 5/16/2023 8:13:16 AM
Final section lower western shearwall approved
|
|
05/18/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | | 5/18/2023 8:00:00 AM
Continued progress at L2 slab supports
|
|
05/25/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 172704 | 5/25/2023 9:39:17 AM
P2 deck approved
|
|
06/01/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 374909 | 6/1/2023 9:26:14 AM
Columns as noted
|
|
06/06/2023 | SHEARWALL | Murray Armstrong | PASS | 451514 | 6/6/2023 9:28:10 AM
Perimeter shot Crete wall, reinforcement at P2 level, as noted on approved plans. 4/0 ground to building steel.
|
|
06/08/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 105416 | 6/8/2023 8:42:48 AM
Remaining western sheer walls
|
|
06/13/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 393705 | 6/13/2023 8:54:55 AM
Final sheer wall western section 1st level above basement
|
|
06/29/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 121903 | 6/29/2023 10:11:22 AM
L2 deck approved
|
|
07/05/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 445007 | 7/5/2023 8:46:22 AM
L1 columns approved
|
|
07/06/2023 | FOOTINGS/FOUNDATION | Phil Brandenburg | PARTIAL | | 7/6/2023 7:55:35 AM
Continued work at level one walls
|
|
07/10/2023 | SHEARWALL | Murray Armstrong | PASS | 112907 | 7/10/2023 11:09:49 AM
Perimeter shot Crete walls at P1 up through mezzanine, and interior sheer wall reinforcement as noted on approved plans
|
|
07/12/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 431017 | 7/12/2023 9:02:37 AM
Remaining shear walls, L-1 level
|
|
07/18/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | | 7/18/2023 4:52:33 PM
L1 shear south
|
|
07/19/2023 | SHEARWALL | Phil Brandenburg | CORRECTIONS | 59712 | 7/19/2023 8:44:17 AM
Not ready
|
|
07/20/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 595423 | 7/20/2023 9:20:18 AM
Remaining L1, shear walls and ramp
|
|
07/31/2023 | GROUT LIFT | Murray Armstrong | PASS | 0408 | 7/31/2023 10:26:53 AM
As noted
7/31/2023 10:27:49 AM
As noted
|
|
08/01/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 235716 | 8/1/2023 7:57:46 AM
Ground level deck approved
|
|
08/02/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 563513 | 8/2/2023 8:42:03 AM
Continued work at ground floor
|
|
08/04/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PASS | 34819 | 8/4/2023 8:51:41 AM
Ground level deck, eastern half
|
|
08/10/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 85922 | 8/10/2023 8:54:38 AM
Remaining L1 deck, except ramp
|
|
09/18/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 1612 | 9/18/2023 8:17:47 AM
Small ground level walls as noted
|
|
09/25/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 83611 | 9/25/2023 9:33:08 AM
Ground level, sheer walls and column as noted
|
|
10/09/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 434612 | 10/9/2023 8:45:41 AM
Shear walls as noted
|
|
10/10/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | | |
|
10/12/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 415526 | 10/12/2023 9:01:02 AM
Continued ground level, sheer walls as noted
|
|
10/13/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | | |
|
10/16/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | | 10/16/2023 6:23:02 AM
ground level as noted
|
|
10/17/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | | 10/17/2023 6:17:07 AM
continued shear walls
|
|
10/18/2023 | SHEARWALL | Phil Brandenburg | CORRECTIONS | 91027 | 10/18/2023 11:56:49 AM
Canceled per contractor
|
|
10/20/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 154622 | 10/20/2023 8:09:04 AM
Radius wall as shown on plan ground level
|
|
10/25/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 485226 | 10/25/2023 9:22:43 AM
Small decks as noted
|
|
11/02/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | | |
|
11/07/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 29014 | 11/7/2023 8:51:03 AM
Shear walls only at western portion of site
|
|
11/07/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 255013 | 11/7/2023 8:51:05 AM
Shear walls only at western portion of site
|
|
11/08/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 291505 | 11/8/2023 9:12:02 AM
Second floor deck, approved, pending minor change, RFI
|
|
11/22/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 561921 | 11/22/2023 9:32:40 AM
Shear walls as noted.
Also verified underground for generator
|
|
11/28/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 523303 | 11/28/2023 8:54:00 AM
Second level walls as noted
|
|
12/05/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 194904 | 12/5/2023 8:14:34 AM
Ramp rebar as noted
|
|
12/06/2023 | INTERIOR DRYWALL | VCA3 | PARTIAL | 363424 | 12/6/2023 11:27:46 AM
Provide fire tapping at shaft wall joint
|
|
12/07/2023 | INTERIOR DRYWALL | VCA3 | CORRECTIONS | 38025 | 12/7/2023 11:14:19 AM
Not ready
|
|
12/18/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 531326 | 12/18/2023 8:19:05 AM
Level two western deck
|
|
01/05/2024 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 17310 | 1/5/2024 7:09:49 AM
Continued observations of second-floor concrete areas
|
|
01/08/2024 | STRUCTURAL CONCRETE | Murray Armstrong | PARTIAL | 73416 | 1/8/2024 9:52:33 AM
Sheer walls at L2, west elevation, partial
|
|
01/09/2024 | SHEARWALL | Phil Brandenburg | PARTIAL | 61841 | 1/9/2024 8:21:47 AM
Second level walls and columns as noted
1/9/2024 8:29:07 AM
Second level walls and columns as noted
1/9/2024 8:37:30 AM
Second level walls and columns as noted
1/9/2024 8:47:35 AM
Second level walls and columns as noted
1/9/2024 8:53:22 AM
Second level walls and columns as noted
1/9/2024 9:15:31 AM
Second level walls and columns as noted
1/9/2024 10:07:34 AM
Second level walls and columns as noted
|
|
01/29/2024 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 312315 | 1/29/2024 8:19:57 AM
Third level east deck approved
|
|
02/09/2024 | SHEARWALL | Phil Brandenburg | PARTIAL | 36809 | 2/9/2024 9:15:00 AM
Third level shear walls as noted
|
|
02/12/2024 | SHEARWALL | Phil Brandenburg | PARTIAL | 364910 | 2/12/2024 8:31:27 AM
Remaining third floor, sheer walls
|
|
02/27/2024 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 83712 | 2/27/2024 8:30:41 AM
Third-floor west deck
|
|
02/28/2024 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 554019 | 2/28/2024 8:21:16 AM
Third floor columns
Waste and storm drain systems P1 level
|
|
| SHEARWALL | INSPECTOR BUCKET | | | |
|
04/04/2024 | FOOTINGS/FOUNDATION | Phil Brandenburg | PARTIAL | | 4/4/2024 9:46:40 AM
Third-floor roof slab complete
|
|
04/10/2024 | STRUCTURAL CONCRETE | Phil Brandenburg | PASS | 59227 | 4/10/2024 8:09:45 AM
Roof
|
|
04/17/2024 | INTERIOR DRYWALL | Phil Brandenburg | PARTIAL | 303908 | 4/17/2024 8:06:13 AM
Interior walls at mechanical rooms as noted
|
|
04/17/2024 | INTERIOR WALL FRAMG | Phil Brandenburg | PARTIAL | 283807 | 4/17/2024 8:06:16 AM
Interior walls at mechanical rooms as noted
|
|
04/22/2024 | RATED SHAFT CONSTR | Phil Brandenburg | PARTIAL | 51825 | 4/22/2024 7:55:42 AM
Various rated walls, drywall, and framing as noted
|
|
04/23/2024 | STEEL FRAMING | Phil Brandenburg | PARTIAL | 103506 | 4/23/2024 8:44:57 AM
Progress inspection at lower levels approved
|
|
04/23/2024 | INSULATION | Phil Brandenburg | PARTIAL | 40826 | 4/23/2024 8:45:00 AM
Progress inspection at lower levels approved
|
|
04/24/2024 | INSULATION | Phil Brandenburg | PARTIAL | 54404 | 4/24/2024 8:12:26 AM
Progress inspection, various floors, including framing, and drywall
|
|
04/25/2024 | PRE WRAP | Phil Brandenburg | PARTIAL | 83005 | 4/25/2024 7:57:11 AM
Framing and drywall inspections, various levels
|
|
04/25/2024 | INTERIOR DRYWALL | Phil Brandenburg | PARTIAL | 545920 | 4/25/2024 7:57:14 AM
Framing and drywall inspections, various levels
|
|
04/25/2024 | INTERIOR WALL FRAMG | Phil Brandenburg | PARTIAL | 534819 | 4/25/2024 7:57:16 AM
Framing and drywall inspections, various levels
|
|
05/01/2024 | RATED SHAFT CONSTR | Phil Brandenburg | PARTIAL | 194218 | 5/1/2024 8:21:13 AM
Various shaft walls multiple levels
|
|
05/02/2024 | INTERIOR WALL FRAMG | Phil Brandenburg | PARTIAL | 203519 | |
|
05/03/2024 | ROUGH FRAMING | Phil Brandenburg | PARTIAL | | 5/3/2024 8:12:21 AM
Ongoing framing and drywall at P1 level and ground level
|
|
05/03/2024 | INTERIOR DRYWALL | Phil Brandenburg | PARTIAL | 223520 | 5/3/2024 8:12:24 AM
Ongoing framing and drywall at P1 level and ground level
|
|
05/07/2024 | ROUGH FRAMING | Phil Brandenburg | PARTIAL | | 5/7/2024 7:55:41 AM
Insulation at various walls, various floors
|
|
05/10/2024 | INTERIOR DRYWALL | Phil Brandenburg | PARTIAL | | 5/10/2024 8:39:36 AM
Various walls at P1, P2, and L1 as noted
|
|
| INTERIOR DRYWALL | Phil Brandenburg | | | |
|