09/21/2022 | FOOTINGS FOUNDATION | Phil Brandenburg | PASS | 451504 | |
|
10/19/2022 | STRUCTURAL CONCRETE | Phil Brandenburg | PASS | 285903 | |
|
11/22/2022 | STRUCTURAL CONCRETE | VCA3 | PARTIAL | 505203 | 11/22/2022 7:17:52 AM
2nd floor wall steel pending SOR
|
|
01/30/2023 | FLOOR SHEATHING | Murray Armstrong | PASS | 31503 | 1/30/2023 9:54:07 AM
Unit 8 L-2
|
|
02/15/2023 | FLOOR SHEATHING | Phil Brandenburg | PASS | 313225 | |
|
02/21/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 415825 | 2/21/2023 9:58:44 AM
Mid-level tilt up type shear wall approved
|
|
02/22/2023 | PRE WRAP | Phil Brandenburg | PARTIAL | 283018 | 2/22/2023 9:40:28 AM
Tyvek application at shear walls
|
|
03/29/2023 | FLOOR SHEATHING | Phil Brandenburg | PASS | 261802 | |
|
04/07/2023 | SHEARWALL | Phil Brandenburg | PARTIAL | 232509 | 4/7/2023 9:23:49 AM
OK to install windows at exterior nailing approved around window areas
|
|
07/17/2023 | ROOF SHEATHING | Murray Armstrong | PASS | 522513 | 7/17/2023 10:12:26 AM
Shower pans at unit six through nine
7/17/2023 10:12:47 AM
Shower pans at unit six through nine
|
|
08/04/2023 | EXTERIOR LATH | Phil Brandenburg | PARTIAL | 551708 | 8/4/2023 9:22:25 AM
Progress inspection approved
|
|
| INTERIOR LATH | INSPECTOR BUCKET | | 25233 | |
|
08/09/2023 | ROUGH FRAMING | Phil Brandenburg | PARTIAL | 31518 | 8/9/2023 10:12:24 AM
First four units, interior lath inspection approved
Southern four units
|
|
08/14/2023 | INSULATION | Phil Brandenburg | PARTIAL | 332808 | 8/14/2023 10:05:26 AM
Drywall first two units from Street southside
|
|