05/19/2022 | STEEL FRAMING | Phil Brandenburg | CORRECTIONS | 264502 | 5/19/2022 9:24:58 AM
Superintendent not around
Unknown what inspection was for no steel framing observed
|
|
06/01/2022 | STEEL FRAMING | Phil Brandenburg | CORRECTIONS | | 6/1/2022 10:01:28 AM
Site meeting only
6/1/2022 10:02:32 AM
Site meeting only
|
|
06/02/2022 | FLOOR SHEATHING | Phil Brandenburg | PARTIAL | 533910 | 6/2/2022 7:41:39 AM
Needed underground for behind curb approved
|
|
06/02/2022 | FLOOR SHEATHING | Phil Brandenburg | PARTIAL | 521502 | 6/2/2022 7:41:42 AM
Needed underground for behind curb approved
|
|
06/07/2022 | DENSGLASS | Phil Brandenburg | PARTIAL | 264902 | 6/7/2022 10:53:13 AM
Curbs and balards per plan
|
|
06/08/2022 | EXTERIOR LATH | Phil Brandenburg | PARTIAL | 461605 | 6/8/2022 9:15:46 AM
Site meeting only
|
|
| EXTERIOR LATH | INSPECTOR BUCKET | | | |
|
07/05/2022 | FINAL BUILDING** | Phil Brandenburg | CORRECTIONS | 353102 | 7/5/2022 8:33:31 AM
Needed electrical release
Provide third-party testing for main breakers 800 amp and over
Provide torque testing
|
|
07/11/2022 | FINAL BUILDING** | Phil Brandenburg | CORRECTIONS | 54302 | 7/11/2022 10:00:01 AM
Install power and test all systems
ADA spaces per tesla contract approved
|
|
07/12/2022 | FINAL BUILDING** | Phil Brandenburg | CORRECTIONS | | 7/12/2022 8:38:37 AM
Not ready
|
|
07/13/2022 | RATED SHAFT CONSTR | Phil Brandenburg | PARTIAL | | 7/13/2022 8:47:33 AM
Site meeting to discuss ADA parking
|
|
09/02/2022 | FINAL BUILDING** | Phil Brandenburg | PASS | | |
|