07/11/2022 | FOOTINGS FOUNDATION | Phil Brandenburg | PARTIAL | 162407 | 7/11/2022 10:53:12 AM
Lower pad footings and tree well approved
|
|
08/11/2022 | FOOTINGS FOUNDATION | Phil Brandenburg | PARTIAL | 485602 | 8/11/2022 10:22:03 AM
Grade beam and tree well walls
|
|
08/25/2022 | FOOTINGS FOUNDATION | Phil Brandenburg | PARTIAL | 33512 | 8/25/2022 9:09:20 AM
Continued grade beams
|
|
10/05/2022 | INTERIOR WALL FRAMG | Phil Brandenburg | PARTIAL | 404002 | 10/5/2022 9:20:05 AM
Site meeting only
|
|
11/10/2022 | INTERIOR WALL FRAMG | VCA3 | PARTIAL | 33905 | 11/10/2022 7:21:32 AM
Meeting discussing potential of covering roof
|
|
11/18/2022 | INTERIOR WALL FRAMG | Phil Brandenburg | PARTIAL | 75910 | 11/18/2022 10:12:42 AM
Site meeting only
|
|
11/22/2022 | INTERIOR WALL FRAMG | Phil Brandenburg | PARTIAL | 34302 | 11/22/2022 9:39:23 AM
Approved roof sheeting per engineer
|
|
12/21/2022 | FOOTINGS FOUNDATION | VCA3 | CORRECTIONS | 442102 | 12/21/2022 10:06:10 AM
Supply approved detail tying A footing to continuous footing and new footings to existing
|
|
12/26/2022 | FOOTINGS FOUNDATION | Murray Armstrong | PASS | 05002 | 12/26/2022 9:23:14 AM
For addition at rear of existing building
|
|
12/27/2022 | FOOTINGS/FOUNDATION | Murray Armstrong | PASS | | 12/27/2022 12:05:31 PM
On site yesterday 12/26 for footing approval. SOR uploaded to system today 12/27
|
|
01/12/2023 | FOOTINGS FOUNDATION | VCA3 | PARTIAL | 203911 | 1/12/2023 8:38:51 AM
Slot cut B with soils report pending SOR and deputy report
|
|
01/20/2023 | FOOTINGS FOUNDATION | VCA3 | PARTIAL | 195821 | 1/20/2023 1:41:47 PM
Slot cut C and slab with soils report. Pending SOR
|
|
01/20/2023 | FOOTINGS FOUNDATION | VCA3 | PARTIAL | 81906 | 1/20/2023 1:41:50 PM
C cut and slab with soils report
Pending SOR
|
|
01/30/2023 | FOOTINGS FOUNDATION | Murray Armstrong | PASS | 105915 | 1/30/2023 8:44:40 AM
Received SOR and deputies report
|
|
02/09/2023 | INTERIOR WALL FRAMG | VCA3 | PARTIAL | 161602 | 2/9/2023 11:55:07 AM
Small roof at top of stairs: sheathing
|
|
03/01/2023 | RATED SHAFT CONSTR | Phil Brandenburg | PARTIAL | 71311 | 3/1/2023 9:21:32 AM
Full framing inspection
|
|
03/01/2023 | T-BAR CEILINGS | Phil Brandenburg | PARTIAL | 65410 | 3/1/2023 9:21:35 AM
Full framing inspection
|
|
03/01/2023 | STEEL FRAMING | Phil Brandenburg | PASS | 63009 | |
|
03/01/2023 | INTERIOR WALL FRAMG | Phil Brandenburg | PASS | 6607 | |
|
03/01/2023 | FLOOR SHEATHING | Phil Brandenburg | PASS | 61708 | |
|
03/01/2023 | SHEARWALL | Phil Brandenburg | PASS | 53705 | |
|
03/01/2023 | ROUGH FRAMING | Phil Brandenburg | PASS | 54906 | |
|
03/09/2023 | INSULATION | VCA3 | PASS | 381135 | |
|
03/13/2023 | SHEARWALL | Murray Armstrong | PASS | 505714 | 3/13/2023 10:17:07 AM
At east wall L-1 and L-2
|
|
04/14/2023 | INTERIOR DRYWALL | Phil Brandenburg | PASS | 422718 | |
|
04/21/2023 | EXTERIOR LATH | Phil Brandenburg | PASS | 241526 | |
|
05/02/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 49310 | 5/2/2023 9:37:31 AM
Stair railing, footings, approved
|
|
05/25/2023 | INTERIOR LATH | Phil Brandenburg | CORRECTIONS | 29232 | 5/25/2023 10:04:33 AM
Paper required behind backer board
|
|
06/13/2023 | FOOTINGS FOUNDATION | Phil Brandenburg | CORRECTIONS | 584102 | 6/13/2023 9:30:21 AM
Not ready
|
|
06/15/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 482824 | 6/15/2023 9:09:58 AM
Outdoor fence supports approved
|
|
06/20/2023 | FOOTINGS FOUNDATION | Phil Brandenburg | CORRECTIONS | 415910 | 6/20/2023 10:18:25 AM
Not ready
|
|
06/27/2023 | FOOTINGS FOUNDATION | VCA3 | PASS | 585406 | 6/27/2023 7:28:35 AM
Pads for trellis at driveway with SOR and soils
|
|
07/13/2023 | FOOTINGS FOUNDATION | Phil Brandenburg | CORRECTIONS | 424002 | 7/13/2023 9:11:29 AM
Unable to locate superintendent
Only footing work observed, was not completed at time of inspection
|
|
07/14/2023 | STRUCTURAL CONCRETE | Phil Brandenburg | PASS | | 7/14/2023 6:55:50 AM
exterior hardscape improvements
|
|
07/27/2023 | FINAL BUILDING** | Phil Brandenburg | CORRECTIONS | 304516 | 7/27/2023 9:29:00 AM
Finish all exterior work
Add ADA placard's as discussed
Provide fire department approval
Provide air balance
Provide green building submittals
|
|
08/03/2023 | FINAL BUILDING** | Phil Brandenburg | CORRECTIONS | 81515 | 8/3/2023 9:03:18 AM
Finish ADA parking stall
|
|
08/08/2023 | FINAL BUILDING** | VCA3 | PASS | 213507 | |
|