03/15/2022 | STRUCTURAL CONCRETE | Phil Brandenburg | PARTIAL | 191005 | 3/15/2022 10:15:58 AM
Collected all soils reports for all shoring work
|
|
03/15/2022 | FOOTINGS FOUNDATION | Phil Brandenburg | PARTIAL | 183304 | 3/15/2022 10:16:01 AM
Collected all soils reports for all shoring work
|
|
05/02/2022 | FOOTINGS FOUNDATION | Phil Brandenburg | PARTIAL | 392804 | 5/2/2022 10:42:19 AM
Site meeting regarding plumbing questions
Collected SOR report for rebar in foundation
|
|
06/14/2022 | FOOTINGS/FOUNDATION | Phil Brandenburg | PASS | | 6/14/2022 1:27:25 PM
mat slab and walls
|
|
07/20/2022 | STRUCTURAL CONCRETE | Phil Brandenburg | PASS | 361603 | 7/20/2022 9:39:00 AM
Perimeter walls approved
|
|
07/20/2022 | FOOTINGS FOUNDATION | Phil Brandenburg | PARTIAL | 365404 | 7/20/2022 9:39:03 AM
Perimeter walls approved
|
|
11/17/2022 | STRUCTURAL CONCRETE | VCA3 | CORRECTIONS | 27704 | 11/17/2022 10:23:37 AM
Not ready
|
|
11/17/2022 | ROUGH FRAMING | VCA3 | PARTIAL | 264003 | 11/17/2022 10:23:40 AM
Steel beams and posts in basement
|
|
11/17/2022 | STEEL FRAMING | VCA3 | PARTIAL | 255902 | 11/17/2022 10:23:42 AM
Steel beams and posts in basement
Picked up deputy report for bolting and welding
Supply SOR and Mill Certs
|
|
12/07/2022 | ROUGH FRAMING | VCA3 | PASS | 282404 | 12/7/2022 10:18:37 AM
Heavy steel in basement with SOR, mill ceros, and shop certified
|
|
12/07/2022 | STEEL FRAMING | VCA3 | PASS | 275003 | 12/7/2022 10:18:39 AM
Heavy steel in basement with SOR, mill Certs, and shop fabrication certification
|
|
12/07/2022 | FOOTINGS FOUNDATION | VCA3 | PASS | 27902 | 12/7/2022 10:18:41 AM
Slab extension and footing with SOR
|
|
01/03/2023 | FLOOR SHEATHING | VCA3 | PARTIAL | 232102 | 1/3/2023 11:22:25 AM
Provide SOR
1/3/2023 11:23:18 AM
Provide SOR
1/3/2023 1:15:27 PM
Provide SOR
|
|
01/24/2023 | ROUGH FRAMING | VCA3 | PARTIAL | 125123 | 1/24/2023 7:24:51 AM
2nd floor sheathing & nailing with SOR
|
|
01/30/2023 | FLOOR SHEATHING | Murray Armstrong | CORRECTIONS | 394411 | 1/30/2023 9:54:08 AM
No one on site, gate locked, I posted a door hanger
|
|
01/31/2023 | ROUGH FRAMING | VCA3 | CORRECTIONS | 405513 | 1/31/2023 12:51:50 PM
Not ready
|
|
01/31/2023 | ROOF SHEATHING | VCA3 | PASS | 402312 | |
|
02/01/2023 | SHEARWALL | VCA3 | PARTIAL | 412314 | 2/1/2023 7:25:39 AM
Roof nailing approved
|
|
03/22/2023 | ROUGH FRAMING | Phil Brandenburg | CORRECTIONS | 111323 | 3/22/2023 9:13:34 AM
OK to flash windows only pending structural observation of exterior by engineer
|
|
03/22/2023 | STEEL FRAMING | Phil Brandenburg | CORRECTIONS | 103622 | 3/22/2023 9:13:36 AM
OK to flash windows only pending structural observation of exterior by engineer
|
|
03/22/2023 | SHEARWALL | Phil Brandenburg | CORRECTIONS | 10321 | 3/22/2023 9:13:38 AM
OK to flash windows only pending structural observation of exterior by engineer
|
|
03/29/2023 | PRE WRAP | VCA3 | PARTIAL | 241107 | 3/29/2023 11:14:44 AM
Exterior shear previously approved but obtained S O R and deputy report
|
|
03/29/2023 | SHEARWALL | VCA3 | PASS | 23206 | 3/29/2023 11:14:46 AM
Exterior previously approved, obtained SOR and deputy report
|
|
06/30/2023 | ROUGH FRAMING | VCA3 | CORRECTIONS | 593402 | 6/30/2023 10:34:43 AM
Not ready
|
|
09/14/2023 | ROUGH FRAMING | Phil Brandenburg | PARTIAL | 311316 | 9/14/2023 9:54:00 AM
Approved, pending structural observation
9/14/2023 10:02:42 AM
Approved, pending structural observation
|
|
09/15/2023 | ROUGH FRAMING | Phil Brandenburg | PARTIAL | | 9/15/2023 6:39:10 AM
received structural observation
|
|
09/19/2023 | ROUGH FRAMING | VCA3 | PASS | 175910 | |
|
09/27/2023 | ROUGH FRAMING | Phil Brandenburg | PASS | 52316 | |
|
10/02/2023 | EXTERIOR LATH | Phil Brandenburg | PASS | 575202 | |
|
10/05/2023 | EXTERIOR LATH | Phil Brandenburg | CORRECTIONS | 114905 | 10/5/2023 9:00:43 AM
Still not complete
|
|
10/17/2023 | EXTERIOR LATH | VCA3 | PARTIAL | 134724 | 10/17/2023 10:11:53 AM
Provide insulation certificate
|
|
10/17/2023 | INSULATION | VCA3 | PARTIAL | 12923 | 10/17/2023 10:11:56 AM
Provide insulation certificate
|
|
11/03/2023 | INTERIOR DRYWALL | Phil Brandenburg | PARTIAL | 55204 | 11/3/2023 8:56:19 AM
Also approved exterior lath
|
|
11/03/2023 | INTERIOR DRYWALL | Phil Brandenburg | PARTIAL | 51503 | 11/3/2023 8:56:21 AM
Also approved exterior lath
|
|
11/06/2023 | EXTERIOR LATH | VCA3 | PASS | 512002 | |
|
11/09/2023 | EXTERIOR LATH | Phil Brandenburg | PASS | 524203 | |
|
11/09/2023 | INTERIOR DRYWALL | Phil Brandenburg | PASS | 52702 | |
|
02/23/2024 | INTERIOR LATH | Phil Brandenburg | PASS | | 2/23/2024 6:32:24 AM
remaining hardy backer
|
|
03/19/2024 | FOOTINGS FOUNDATION | Phil Brandenburg | PARTIAL | 41512 | 3/19/2024 8:50:23 AM
Needed rear deck with bonding approved
|
|
03/19/2024 | FLOOR SHEATHING | Phil Brandenburg | CORRECTIONS | 45313 | 3/19/2024 8:50:27 AM
Only needed deck bonding
|
|